2024-2025 Asphalt Resurfacing Program: Roads, Laneways, and Footpath

  • Project typeRoad Rehabilitation Program
  • Project scheduleNovember 2023 to April 2024
RR20232024.jpg

Last Update:18/02/2025

The Town of Cambridge has a total of 190 kilometers of sealed roads and lanes (ROWs). The resurfacing program is initially scheduled based on the surface age of each section of pavement, with general base intervals as follows:

  • Lanes and Paths: every 30-35 years
  • Access Roads: every 30 years
  • Local Distributor Roads: every 25 years
  • District Distributor B Roads: every 20 years
  • District Distributor A Roads: every 15 years

This schedule is then adjusted according to the specific condition of each road section, taking into account factors like rutting, cracking, and surface repairs. The proactive maintenance program aims to resurface an average of 4.35 kilometers per year.

By coordinating resurfacing efforts in nearby areas, this approach maximises efficiency and minimises disruption for the community. This maintenance strategy ensures that local roads remain in good condition, typically resurfaced every 25 to 35 years, demonstrating a commitment to preserving the quality and accessibility of vital road infrastructure for all.

2024 to 2025 Program

All projects – Enabling Works: September to November 2024. These works identify the locations of underground services such as gas, water, power and communications

Roads

Belford Road Chipping Rd - Clovelly Rd, City Beach 

  • Complete

Rosslyn St Railway Rde - Cul de-sac, West Leederville

  • Proposed construction, April 2025

Argyle St Kimberley St - Coldstream St, West Leederville

  • Scheduled 19 February 2025

Connaught St Coldstream St - Barrington St, West Leederville

  • Scheduled 18 February 2025

Carlton St Woolwich St - Connaught St, West Leederville

  • Scheduled 20 February 2025

Marlow St Salvado Rd - Cambridge St, Wembley

  • Scheduled 3-28 February 2025

Caddy Ave Vincent St to Kimberley St, West Leederville

  • Proposed construction - April 2025

Brighton St Coldstream St - Cul de sac, West Leederville

  • Scheduled 18-19 February 2025

Loftus St (Northbound) - Railway Pd to Cambridge St, West Leederville 

  • Proposed construction March to April 2025

 

Laneways

Construction Dates:

Kneebone Lane

  • Complete

Brich Lane

  • Complete

Levitt Lane

  •  Complete

Pathways

The Boulevard Pathway – Caithness to Seymour Ave

  • Scheduled 24-27 March 2025

What to Expect During The Works

Local residents will receive notification about the works 1-2 weeks before they begin. Due to the nature of the work, sections of the road may be left unsealed and open to traffic at various times, which may lead to increased dust and noise in the immediate area. While this is unavoidable, measures will be implemented to minimize the impact. Speed reductions and detours will be in effect for the duration of the works.

Road Closures and Detours

Notifications about road closures, including specific times, will be posted on this page once the schedule is confirmed. General asphalt resurfacing works are expected to be completed within two to three days. All affected residents will receive direct notifications at least two weeks prior to the start of the work.

 