Leederville Sporting Club - UAT and Access Ramp

  • Project typeFacility Upgrade
  • Project scheduleJanuary 2023 - June 2023
Leederville-Logo.jpg

The project outlines an upgrade of essential elements of the Leederville Sporting Club to bring them into DAIP (Disability access and inclusion plan) compliance. The works will be staged to reduce the impact on the club and reduce the disruption to both local residence and club users.

On completion, the works will improve the disability compliance of the facility to ensure equal opportunity for all users.

Scope Details

 

Stage 1 - Construct a AS1428 compliant UAT (Universal Accessible Toilet) within the existing club room office.

Stage 2 - Provide a compliant front entrance ramp and doorway into the club, extending around the side of the building up to the female toilet entrance. The second stage will provide a compliant walkway to the newly completed UAT and alfresco area, while incorporating AS1428 compliance to the rear doors of the building.

Stage 3 - New grease trap and internal kitchen upgrade.

Stage 4 - Upgrade to alfresco.

 

Progress Updates

 

The construction of the new UAT commenced on 16 January with completion expected February/March. Each stage will commence upon the completion of the previous works to reduce disruption to the club.

 All works are planned to be completed by June 2023.

Leederville Sports Club - UAT and Access Ramp Floorplan.png

 

View Map