Floreat East

  • Project typeUnderground Power
  • Project scheduleStarted
  • Contractor nameCAPE
  • Completion Date30 September 2019

 

Floreat east map.png
Zone Start Date Completion Date
 Zone 1 June 2018 September 2019
Zone 2 August 2018 September 2019
Zone 3 September 2018 September 2019

The project will be split into zones for construction purposes with works proceeding in sequence to minimise the impact on you and your property.

*Technical constraints may require changes to some dates as the project proceeds and you will be advised of these if necessary.