Floreat North

  • Project typeUnderground Power
  • Project scheduleStarted
  • Contractor nameCLA
  • Completion Date30 September 2019

 

   

 

Floreat North Map April 2019.png

 

Zone Start Date Completion Date
Zone 1 June 2018 May 2019
Zone 2 September 2018 May 2019
Zone 3 December 2018 September 2019
Zone 4 February 2019 September 2019
 Zone 5 April 2019 September 2019

The project will be split into zones for construction purposes with works proceeding in sequence to minimise the impact on you and your property.

*Technical constraints may require changes to some dates as the project proceeds and you will be advised of these if necessary.