Wembley West Leederville

  • Project typeUnderground Power
  • Project schedule Contractor currently working in Zone 1
  • Contractor nameCLA
  • Completion Date31 March 2020

WWL ZoneMap.JPG

 
 Zone   Estimated Start Date Estimated Completion Date 
 Zone 1  November 2018  October 2019
 Zone 2   March 2019  November 2019
 Zone 3  May 2019  December 2019
 Zone 4  September 2019  March 2020

The project will be split into zones for construction purposes with works proceeding in sequence to minimise the impact on you and your property.

*Technical constraints may require changes to some dates as the project proceeds and you will be advised of these if necessary.