Foreshore Management Plan
- Project scheduleSeptember 2024 - August 2026
Last Updated:19/12/2024
The Town of Cambridge has received 50% funding from the Western Australian Planning Commission and administered through the Department of Planning Lands and Heritage, to develop a 10yr Foreshore Management Plan.
A key recommendation in the Town’s Coastal Hazard Risk Management Adaptation Plan (CHRMAP) 2022 is to develop a Foreshore Management Plan (FMP) to guide future maintenance and planning of the Town’s coastline.
The objective is to establish a management framework to guide planning, development, rehabilitation and long-term management of the Town's coastal foreshore reserve areas.
Project Schedule
- Review scope of works Sept/October 2024
- Advertise Tender November 2024
- Appoint Consultant December 2024
- Inception Meeting January 2025
- Finalise Community Engagement Strategy February 2025
- Review Draft Foreshore Management Plan December 2025
- Community Feedback January 2026
- Review final Foreshore Management Plan May 2026
- Council endorsement and publish on website August 2026
Project Updates
The Tender process is complete and the Town has appointed Land Insights to produce the Foreshore Management Plan.