Perry Lakes Replenishment Scheme; Pump System Audit
- Project scheduleNovember 2025 - March 2026
Last Updated: 10 December 2025
The Perry Lakes replenishment scheme was implemented to re-establish permanent water in Perry Lakes, by diverting excess water from the Herdsman Main Drain into Perry Lakes. The project involved upgrading and improving existing drainage infrastructure and installing of a pump station next to Newman College.
Since its inception in 2023 the Perry Lakes replenishment scheme has produced inconsistent outcomes, and an audit of the pump system has been proposed to investigate the performance of the scheme and make recommendations to bring the scheme in line with community expectations.
Project Schedule
- Engagement and creation of working group – August 2025
- Scope development September - October 2025
- Procurement of services – November – December 2025
- Audit phase January – March 2026
- Report findings and recommendations – June 2026
Progress Updates
The project working group consists of Town of Cambridge Parks officers, Local Residents and members of the Friends of Perry Lakes. This group holds a diverse skill set and local knowledge, including hydrogeology and engineering. The scope for the consultancy services has been developed through correspondence and in-person meetings with the project working group.
The agreed scope of works has been issued to a number of qualified and experienced consultants to commence the procurement process.