Perry Lakes Replenishment Scheme; Pump System Audit

  • Project scheduleJanuary 2026 - April 2027
Pump Audit.jpg

Last Updated: 29 September 2026

The Perry Lakes replenishment scheme was implemented to re-establish permanent water in Perry Lakes, by diverting excess water from the Herdsman Main Drain into Perry Lakes. The project involved upgrading and improving existing drainage infrastructure and installing of a pump station next to Newman College.

Since its inception in 2023 the Perry Lakes replenishment scheme has produced inconsistent outcomes, and an audit of the pump system has been proposed to investigate the performance of the scheme and make recommendations to bring the scheme in line with community expectations.

Project Schedule

  • Engagement and creation of working group – August 2025
  • Scope development September - October 2025
  • Procurement of services – November – December 2025
  • Audit phase January – June 2026
  • Report findings and recommendations – July 2026
  • Implement recommendations from the consultant investigation report – October 2026 – April 2027

Progress Updates

A project working group comprising Town officers, local residents and Friends of Perry Lakes representatives helped shape the consultancy scope through meetings and correspondence.

The system scheme audit has been completed, including review of design, maintenance and performance records, staff consultation, and site inspections. The consultant has provided recommendations, and the project will now progress to the prioritised implementation of the recommended actions.