Depot Power Supply Upgrade
- Project scheduleDesign: 2025 | Construction: early-mid 2026
Last updated: 12 September 2025
Background
The Town Works Depot Grounds have several buildings, including offices, carports, sheds, washdown, and stores. The facility opened in 1997, and most existing structures were built around this time.
This project intends to upgrade the depot’s power supply to allow capacity for two DC Type 1 electric vehicle (EV) fast chargers. The use of these chargers will complement the existing fleet of EVs and chargers at the admin centre, rolled out in mid-2025.
Refer to the Town’s article regarding EVs, dated 3 July 2025 (link).
Scope of works
- Complete the Western Power application process undertaken by an electrical consultant on behalf of the Town.
- Western Power to design and construct an upgraded power supply in line with the Town’s application.
Progress updates
September 2025
Western Power detailed design ongoing.
June 2025
Detailed design commenced by Western Power.
May 2025
Application submitted to Western Power.
Location
21 Lemnos St, Shenton Park WA 6008. View map.