Lake Monger Drive/South Galup Irrigation System Replacement
- Project typeReplacing or Upgrading Existing Infrastructure
- Project scheduleMarch 2026 - May 2026
Last Updated : 28 January 2026
The Town of Cambridge has recently completed a masterplan that covers the multiple bores and associated irrigation systems that service the Galup Reserve.
As part of that process the two bore systems that service Lake Monger Drive and South Galup were prioritised for replacement in the 2025/26 Financial year.
Replacement will include all pipework, valves and sprinklers with new cubicles and pumps.
Some areas of the reserve are being removed from the irrigation system to reduce water use. These areas will be mulched and revegetated with native planting. This initiative is part of the Kep Katitjin-Gabi Kaadadjan Waterwise action plan funded by the Government of Western Australia and will be delivered by the Town of Cambridge.
Project Schedule:
- Detailed design Sept/October 2025
- Engagement: February - March 2026
- Mulching of non irrigated areas: March - April 2026
- Installation: April - May 2026
Progress Updates
Design and procurement are complete. Irrigation works are being scheduled. Earthworks and Mulching of non irrigated areas is due to commence in March 2026.
Area to be removed from irrigation system, mulched and revegetated.