Roads, Laneways, Car Parks and Pathways - Renewal Programs

  • Project scheduleSeptember 2025 - April 2026
mrrg2.png

Last reviewed: 18/09/2025

Road Rehabilitation Program

Maintaining the integrity of our roads is essential for safety, comfort, and long-term value. The Town of Cambridge's Road Rehabilitation Program ensures that our network of 190 km of sealed roads and laneways continues to meet the needs of our growing community.

Why Road Rehabilitation Matters

Well-maintained roads:

  • Reduce wear on vehicles
  • Minimise traffic disruptions
  • Enhance safety for all users
  • Lower long-term maintenance costs

Funding is provided by the Town, Federal and State Governments under the State funding program.

Assessment Process

Each project begins with a thorough pavement investigation, including:

  • Surface distress analysis: cracking, rutting, patching, and depressions
  • Traffic load assessment
  • Review of resurfacing/rehabilitation history

This ensures we select the most appropriate treatment for each road section.

Rehabilitation Methods

1. Resurfacing

Used when the underlying structure is sound and expected to last another 20+ years. Process:

  • Remove top asphalt layer
  • Apply a new asphalt surface Analogy: Like replacing the carpet on a sturdy floor
2. Pavement Rehabilitation

Needed when deeper structural issues are found. Process:

  • In-situ stabilization to rebuild the pavement’s foundation
  • Designed to extend service life and prevent early failure

Maintenance Guidelines

We target roads based on age and condition. Here's the general resurfacing schedule:

Road Category Interval
Lanes & Paths 30-35 Years
Access Roads 30 Years
Local Distributor Roads 25 Years
 District Distributor B 20 Years
District Distributor A 15 Years

These are adjusted based on real-time inspections of each road section

Annual Goals

  • Prioritise roads showing distress and older than 20 years

  • Coordinate nearby works to reduce community impact and maximise efficiency

mrrg1.png

Stay Informed

We’re dedicated to keeping our community updated on the progression of projects. Advance notice is provided for upcoming projects and works in your area. You can also explore our interactive road works map or contact our Engineering Services team for more information.

Reconstruction Program

1. Cambridge St (Station St to Gregory St westbound)

Scheduled – 9 and 12 October 2025

 Community Notifications

  • Advance Letters: Delivered starting the week of 15 September 2025
  • Variable Message Boards: Installed on-site during the same week to alert residents and motorists
  • Business Outreach: Town representatives will visit nearby businesses early September to explain the scope and timing of the works
  • Subsequent Letter: Delivered nearer to the commencement of works, within 48 hours.

     

    This is part of the Town of Cambridge’s broader effort to maintain road safety and infrastructure quality under the rehabilitation program. If you’re nearby, expect some temporary disruptions—but also smoother roads ahead.

2. Lake Monger Dr (Kimberley St to St Leonards Av east & westbound) and Gregory St to St Vincents Av east & westbound) Scheduled – 5 to 8, 13 to 17 and 28 to 30 October 2025

3. Underwood Av (Perry Lakes Dr to Meagher DR eastbound & Meagher Dr to Herb Elliot Dr westbound) Scheduled – 11 to 15 and 18 to 21 January 2026

Nightworks

We wish to inform residents that work at the above location will be taking place at night. These works are necessary to ensure long-term improvements to local infrastructure; however, they may result in increased noise levels during nighttime hours. We understand this may cause disruption to sleep and impact general living standards, and we sincerely appreciate your patience and understanding during this time. Where possible, we are taking steps to minimise disturbances, and we’ll keep you updated with any changes to the schedule.

Asphalt Resurfacing Program

Roads
  1. Hovea Cr - (Kingsland to Dampier Av) -Scheduled 13 to 15 October 2025 
  2. Grovedale Rd (Alderbury to Salvado) - Scheduled 13 to 14 November 2025
  3. Marlow Street - (Cambridge St to Herdsman Pd) -19 to 25 November 2025
  4. Highbury St - (Bournville St to Seymour Av) -16 March 2025 and 21 April 2025
  5. Malton Pl - (Pandora to End) - 22 April 2025 and 25 May 2025
  6. Chandler Av West - (Ulster Rd to Clanmel Rd) - Construction dates TBD
  7. Johnson St - (Herdsman Pd to Harborne St) - Construction dates TBD
  8. Joseph St - (Cambridge St to Ruislip St) - Construction dates TBC

     

Laneways
  1. Dargin Lane - Construction dates TBD
  2. Logan Lane - Construction Dates TBD
Paths
  1. Boscombe Av (Torr Pl to Frinton Av) - Construction dates TBD 
  2. Helston Park (Frinton Av to West Coast Highway) - Construction dates TBD

Footpath Replacement Program

  1. Cambridge St (300 to 308 and 1A Holland St) Scheduled 30 September 2025
  2. Jersey St (Cambridge St to 154 Jersey St) Scheduled 30 September

What to Expect During Work

Local residents will receive notification about the upcoming works 1–2 weeks before they begin. The letter will provide an overview of the works, including key dates and times, and outline any specific impacts. Due to the nature of the work, sections of the road may be left unsealed and open to traffic at various times, which may lead to increased dust and noise in the immediate area. While this is unavoidable, measures will be implemented to minimise the impact. Speed reductions and detours will be in effect for the duration of the works.

Road Closures and Detours

Notifications about road closures, including specific times, will be posted on this page once the schedule is confirmed. General asphalt resurfacing works are expected to be completed within two to three days. All affected residents will receive direct notifications at least two weeks prior to the start of the work.

Chandler Av West

• Closed (local traffic only) from Ulster Road to Clanmel Road to facilitate kerb works. 7am to 5pm, 22 to 25 September 2025.

Cambridge St

Station Street to Gregory Street

• Westbound lanes closed, 8pm to 5am, 9 and 12 October 2025. Detour - South on McCourt Street, West onto Salvado Road, North on Harborne Street.

Lake Monger Dr

Kimberley Street to St Leonards Avenue

  • Westbound lanes closed, 8pm to 5am, 5, 6 and 28 October 2025. Detour – South on Southport Street, West on Cambridge Street, North on Harborne Street.
  • Eastbound lanes closed, 8pm to 5am, 7, 8, 29 and 30 October 2025. Detour – South on Harborne Street, East on Cambridge Street, North on Southport Street.

St Vincents Avenue to Gregory Street

  • Westbound lanes closed 8pm to 5am, 13 and 15 October 2025. Detour - South on Kimberley Street, West on Cambridge Street, North on Harborne Street.
  • Eastbound lanes closed, 8pm to 5am, 14 and 16 October 2025. Detour - South on Harborne Street, East on Cambridge Street, North on Northwood Street, East on Vincent Street West, North on Kimberley Street.

View Map