Winmarley Park Playground Replacement
- Project typeReplacement of Existing Infrastructure
- Project scheduleFebruary 2026 - April 2026
Last Updated: 11/09/2025
Winmarley Park Playground in Floreat has been identified as requiring replacement through our playground audit and inspection program and replacement is scheduled to be completed this year.
Scope includes:
- Engagement with residents and park users
- Design
- Installation of new play equipment
- Shade sails are being retained
Project Schedule:
- Engagement and design October/November 2025
- Procurement and production December 2025 – February 2026
- Site works and installation February – April 2026
Progress Updates
Project scoping and engagement is underway.
Winmarley Park Swing
Winmarley Park Playground
View map