Planning Fees
Development Application Fees (Statutory Fees)
Determining a development application (other than for an extractive industry) where the development has not commenced or been carried out and the estimated cost of the development is:
Part 1 - Maximum Fixed Fees
| (a) not more $50,000 |
$147 |
| (b) more than$50,000 but not more than $500,000 |
0.32% of the estimated cost of development |
| (c) more than $500,000 but not more than $2.5 million |
$1,700 0.257% for every $1 over $500,000 |
| (d) more than $2.5 million but not more than $5 million |
$7,161 0.206% for every $1 over $2.5 million |
| (e) more than $5 million but not more than $21.5 million |
$12,633 0.123% for every $1 over $5 million |
| (f) more than $21.5 million |
$34,196 |
| (g) determining an application to amend or cancel development approval |
$295 (maximum)
|
| Determining a development application (other than for an extractive industry) where the development has commenced or been carried out |
The fee as stated in (a), (b), (c), (d), (e) or (f) above plus, by way of penalty, twice that fee |
| Determining an initial application for the approval of a home occupations where the home occupation has not commenced |
$222 |
| Determining an initial application for the approval of a home occupations where the home occupation has commenced |
$222 plus, by way of penalty, an additional $444 |
| Determining an application for a change of use or for an alteration or extension or change of a non-conforming use to which item 1 does not apply, where the change or alteration/extension has not commended or been carried out |
$295 |
| Determining an application for a change of use or for an alteration or extension or change of a non-conforming use to which item 2 does not apply, where the change or alteration/extension has commenced or been carried out |
$295 plus, by way of penalty, an additional $590 |
Providing subdivision clearance for:
| (a) not more 5 lots |
$73 per lot |
| (b) more than 5 lots but not more than 195 lots |
$73 per lot for the first 5 lots then $35 per lot |
| (c) more than 195 lots |
$7,393 |
Part 2 - Administration Fees: Scheme Amendments, Re-zonings and Structure Plans
| Director |
$88 per hour |
| Manager / Senior Planning Officer |
$66 per hour |
| Planning Officer |
$36.86 per hour |
| Other Staff (ie. Environmental Health Officer etc) |
$36.86 per hour |
| Administration Officer |
$30.20 per hour |
Administration Fees: Town Planning Services
| Reply to Property Settlement Enquiry (statutory fee) |
$73 |
| Written Planning Advice |
$73 |
| Deemed-to-Comply |
$100 - Additions/Alterations
$295 - Single House |
| Other Statutory Certificates (ie. Liquor Control Act Section 40 etc) |
$73 |
| Design Review Panel Meeting - Member's sitting fee |
Cost recovery |
| Advertising of development application letter, if over 20 lots are invited to comment |
$1 per letter |
Development Assessment Panel Application Fees
The Development Assessment Panel Application Fees can be found here.
Scheme Amendments/Rezoning Applications