City Beach Vertical Wall & Groyne Repairs

  • Project scheduleFebruary 2025 to May 2025
CBVWR.png

Last Updated: Project Complete 

The Town of Cambridge manages a number of marine assets located at City Beach and Floreat Beach. These include the Floreat and City Beach Groynes, the City Beach Seawall and City Beach Vertical Wall. In 2023 the Town engaged a coastal and port engineering company to undertake a condition inspection of the Towns marine structures.

The inspection highlighted maintenance repair works required on Floreat Groyne and City Beach vertical wall.

In the 2024-2025 financial year the Town will undertake these maintenance repair works. The project will be part funded by the Department of Transport, who will provide $200,000 through their Coastal Adaptation and Protection Grants.

The video below shows a time-lapse of similar work being carried out on the City Beach Groyne

Progress Updates

Works to the City Beach vertical wall and Floreat Beach groyne have been completed.

GWC.png

 